This page is written by Scotland Heat Pump Grants, an independent information and enquiry service run by SEO Dons Ltd. We are not the Scottish Government, Home Energy Scotland, Warmworks, Ofgem, a council or an installer. This page summarises the Scottish Government's householder guidance. It is not legal advice: your council's planning department makes the final call, and you can ask it before you install.
Air source heat pumps: the Class 6H limits
Class 6H covers the installation, alteration or replacement of an air source heat pump on a dwelling or within its curtilage (its garden or grounds). Some limits apply to every unit, some only to a unit fixed to the house, and some only to a free-standing unit in the garden or grounds. The Scottish Government's guidance says it is not permitted development, so you need planning permission, if:
| Rule | What it means |
|---|---|
| More than one air source heat pump | Only one is allowed on a building or within its curtilage. The guidance says a building here includes a terraced house, a semi-detached house or a block of flats, so a neighbour's unit can count. |
| Fixed to the house: protrudes more than 1 metre | No part of a unit on the house may stick out more than 1 m from the outer surface of an external wall, roof plane, roof ridge or chimney. |
| Fixed to the house: conservation area | In a conservation area, a unit on the house is only allowed at ground floor level and on the rear elevation. |
| Free-standing: in front of the house | No part of a unit in the garden or grounds may be forward of the principal elevation, or of a side elevation that fronts a road. |
| Free-standing: higher than 3 metres | A unit in the garden or grounds, with any resulting structure, must not exceed 3 m in height. |
| World Heritage Site or listed building | Not permitted development within a World Heritage Site or within the curtilage of a listed building. |
Sources: gov.scot: Circular 1/2024 Householder permitted development rights and gov.scot: Householder permitted development rights guidance (updated 2021); Class 6H of the Town and Country Planning (General Permitted Development) (Scotland) Order 1992, as substituted by SSI 2016/126 and amended by SSI 2024/102. Read 1 November 2026.
The conditions that come with it
Even when a heat pump is permitted development, the guidance attaches conditions:
- It must be used only to provide domestic heating or hot water.
- It must comply with MCS Planning Standards or equivalent standards. An MCS-certified installer works to these, and Home Energy Scotland funding requires an MCS installer and product anyway.
- When it is no longer needed for, or capable of, providing domestic heating or hot water, it must be removed as soon as reasonably practicable.
Air source heat pumps are not subject to prior notification or prior approval in Scotland, so if the unit meets the limits and conditions, there is no form to send the council first.
Ground and water source heat pumps
The guidance says permitted development rights allow the installation, alteration or replacement of a ground source heat pump (Class 6D) or a water source heat pump (Class 6E) within the curtilage of a dwellinghouse, and that there are no restrictions on those rights. Ground source systems need space for the ground loop or borehole, but the planning side is simpler than for an air source unit.
Noise and neighbours
The guidance names noise and visual impact as the amenity issues microgeneration can raise for neighbours. The Class 6H condition that the heat pump comply with MCS Planning Standards is how noise is handled for permitted development, so ask the installer to show how the chosen position meets those standards. Where a unit needs planning permission, the council will weigh the effect on neighbours as part of the application.
Flats, terraces and semi-detached homes
Because the one-unit rule applies per building, and a terraced or semi-detached house or a block of flats counts as one building, a second heat pump on the same building needs planning permission even if it is on a different home. The Scottish Government said in its 2025 consultation on permitted development rights that it was not ready to change the rules for flats, terraces and semi-detached homes.
Source: gov.scot: Permitted development rights to support the provision of new homes, consultation (2025), other considerations, read 31 October 2026.
Planning permission and heat pump grants
Planning and funding are separate. You can be eligible for the Home Energy Scotland grant and loan and still need planning permission for where the unit goes, or the other way round. Sort out both before any work starts: Home Energy Scotland will not fund work that has already begun, and the funding agreement is valid for nine months, which gives time for a planning application if one is needed. For the full picture of the schemes, see heat pump grants in Scotland.
Before you install: a quick check
- Is the home a listed building, in its curtilage, or in a World Heritage Site? If yes, apply for planning permission.
- Is it in a conservation area? If yes, a unit fixed to the house must be at ground floor level on the rear elevation to be permitted development.
- Is there already an air source heat pump on the same building, including a neighbour's half of a semi or terrace? If yes, a second one needs permission.
- If the unit is fixed to the house, will it stick out more than 1 m from the wall or roof? If it stands free in the garden or grounds, will it sit in front of the house or a side wall facing a road, or stand more than 3 m high? If yes to either, it needs permission.
- If none of these apply and the installation meets MCS Planning Standards, it is normally permitted development. If in doubt, ask your council.
Use the eligibility checker to see which scheme fits: the result shows on the page with no obligation. If you send your details, we reply by email. Sending an enquiry does not apply for a grant, and the scheme makes every decision. Free official advice is available from Home Energy Scotland.
Frequently asked questions
Do I need planning permission for an air source heat pump in Scotland?
Usually not. It is permitted development under Class 6H if it is the only air source heat pump on the building and meets MCS Planning Standards. A unit fixed to the house must stick out no more than 1 m and, in a conservation area, be at ground floor level on the rear elevation. A free-standing unit in the garden or grounds must not be in front of the principal elevation or a road-facing side elevation, and must be no higher than 3 m.
Do I need planning permission for a ground source heat pump in Scotland?
The Scottish Government's guidance says ground source (Class 6D) and water source (Class 6E) heat pumps within the curtilage of a house are permitted development with no restrictions.
Can I install an air source heat pump on a listed building in Scotland?
Not under permitted development. Class 6H does not apply within the curtilage of a listed building or within a World Heritage Site, so planning permission is needed.
Can two neighbours both have air source heat pumps on a semi-detached house?
Only one air source heat pump per building is permitted development, and a semi-detached or terraced house counts as one building, so the second unit needs planning permission.
Do I need to notify the council before installing a heat pump in Scotland?
Not for permitted development: the guidance says air source heat pumps are not subject to prior notification or prior approval. If the unit falls outside the limits, you need to apply for planning permission.